Condensate Drain Line And Trap Assembly - Thermo Pride CMA1-50N Installation And Service Manual

Gas fired high efficiency furnace, down flow & direct vent (sealed combustion)
Table of Contents

Advertisement

All installations and services must be performed by qualified service personnel.
When the PVC vent and combustion air intake pipes pass through a ceiling, and
a fire stop is required. Refer to the following:
CEILING: Frame out area around where PVC pipe is to penetrate ceiling. Cut a
2-3/8" diameter hole for 2" PVC in the ceiling and a corresponding hole in a
firestop to be made of a minimum of 18 gauge galvanized metal large enough to
cover the entire framed area. Cut PVC pipe so that it extends up past the fire
stop far enough to engage a PVC coupling that will rest on the fire stop and act
as a support. Seal between the pipe coupling and fire stop with high temperature
RTV silicone sealant (see Figure 13). Continue installing PVC pipe to exhaust
vent and combustion air intake termination as described previously.
Figure 13.
K. CONDENSATE DRAIN LINE AND TRAP ASSEMBLY
1. Figure 14 illustrates the typical drain trap connection for a CMA furnace. (Trap
will be installed at factory.) Connect condensate drain trap to building drain
system.
2. An optional condensate neutralizer kit (P/n 320095) is available when gas
furnace condensate needs to be neutralized (pH increased) prior to discharge
into drain system.