termination elbows as shown in Fig. 46, 47 and 48.
For Ventilated Combustion Air Termination, See Fig. 49.
19. Use appropriate methods to seal openings where combus-
tion air pipe and vent pipe pass through roof or sidewall.
WARNING
!
CARBON MONOXIDE POISONING HAZARD
Failure to follow this warning could result in personal injury
or death.
DO NOT use cement to join polypropylene venting systems.
Follow the polypropylene venting system manufacturer's
instructions for installing polypropylene venting systems.
Optional Installation of the Vent Pipe
NOTE:
DO
NOT
USE
POLYPROPYLENE VENTING SYSTEMS.
This option provides a disconnect point for the vent pipe. The vent
pipe must be cemented to the plastic vent pipe adapter to maintain
a sealed vestibule. See Fig. 42.
1. Insert a length of vent pipe through the casing into the
outlet of the vent elbow.
2. Slide the plastic vent pipe adapter over the length of the
vent pipe down to the furnace casing. Mark the pipe where
it is flush with the outlet of the adapter.
3. Remove the pipe from the furnace and the adapter and cut
off any excess pipe.
4. Clean and prime the end of the pipe that is flush with the
vent adapter with a primer that is appropriate for the type of
pipe being used.
5. Re- -insert the pipe through the casing into the vent elbow.
6. Tighten the clamp around the outlet of the vent elbow.
Torque the clamp to 15 lb- -in.
7. Apply cement to the end of the pipe and to the inside of the
plastic vent adapter.
8. Slide the adapter over the vent pipe and align the screw
holes in the adapter with the dimples in the furnace casing.
9. Pilot drill 1/8- -in. screw holes for the adapter in the casing
and secure the adapter to the furnace with sheet metal
screws.
10. Loosen the clamps on the rubber vent coupling.
11. Slide the end of the coupling with notches in it over the
standoffs in the vent pipe adapter.
12. Tighten the clamp of the coupling over the vent pipe
adapter. Torque the lower clamp around the vent pipe
adapter to 15 lb- -in.
13. Pilot drill a 1/8- -in. hole in the combustion air pipe adapter.
14. Complete the vent and combustion air pipe as shown in
"Install the Vent and Combustion Air Pipe."
NOTICE
FOR POLYPROPYLENE VENTING SYSTEMS
When using polypropylene venting systems, all venting
materials used, including the vent terminations, must be from
the same manufacturer.

Installing the Vent Termination

Roof Terminations
A roof termination of any type will require a 4-in. (102 mm)
flashing for a 2 inch (50 mm ND) concentric vent or a 5- -in.
THIS
TECHNIQUE
FOR
diameter (127 mm) flashing for a 3-inch (80 mm ND) concentric
vent kit. For two-pipe or single pipe vent systems, a flashing for
each pipe of the required diameter will be necessary.
It is recommended that the flashing be installed by a roofer or
competent professional prior to installing the concentric vent. The
terminations can be installed on a flat or pitched roof.
Concentric Vent
Single or multiple concentric vent must be installed as shown in
Fig. 46. Maintain the required separation distance between vents
or pairs of vents as shown in Fig. 46 and all clearance shown in
Fig. 44.
NOTE: Follow the instructions of the vent terminal manufacturer.
These instructions are provided as a reference, only.
Cut one 4- -in. (102 mm) diameter hole for 2- -in. (50 mm ND) kit,
or one 5- -in. (127 mm) diameter hole for 3- -in. (80 mm ND) kit in
the desired location.
Loosely assemble concentric vent/combustion air termination
components together using instructions in kit.
Slide assembled kit with rain shield REMOVED through hole in
wall or roof flashing.
NOTE: Do not allow insulation or other materials to accumulate
inside of pipe assembly when installing it through hole.
Disassemble loose pipe fittings. Clean and cement using same
procedures as used for system piping. DO NOT CEMENT
POLYPROPYLENE FITTINGS.
Two- -Pipe (Direct Vent) and Single- -Pipe (Ventilated
Combustion Air) Terminations
Single and two pipe vent terminals must be installed as shown in
Fig. 46 and 47. Maintain the required separation distance between
vents or pairs of vents as shown in Fig. 46 and 47. and all
clearance shown in Fig. 44 and 45.
NOTICE
RECOMMENDED SUPPORT FOR VENT
TERMINATIONS
It is recommended that rooftop vent terminations in excess of
36 inches (1 M) in vertical length be supported by EITHER
the Direct Vent Termination Kit shown in Table 12 or by
field- -supplied brackets or supports fastened to the structure.
Cut the required number of holes in the roof or sidewall for vent
and (when used) combustion air pipes. Sidewall holes for two-pipe
vent terminations should be side-by-side, allowing space between
the pipes for the elbows to fit on the pipes.
Holes in the roof for direct- -vent (two pipe) terminations should be
spaced no more than 18 in. (457 mm) apart to help avoid vent gas
recirculation into combustion air intake.
Termination elbows will be installed after the vent and (if used)
combustion air pipe is installed.
Sidewall Terminations
Concentric Vent Termination
NOTE: Follow the instructions of the vent terminal manufacturer.
These instructions are provided as a reference only.
Determine an appropriate location for termination kit using the
guidelines provided in section "Locating The Vent Termination" in
this instruction.
1. Cut one 4- -in. diameter hole for 2- -in. kit, or one 5- -in. dia-
meter hole for 3- -in. kit.
2. Loosely assemble concentric vent/combustion air termina-
tion components together using instructions in kit.
3. Slide assembled kit with rain shield REMOVED through
hole.
46