Step 9.
Twist-lock the vent cap and seal.
Note: For multi-story vertical installations, a ceiling firestop
is required at the second floor, and any subsequent floors
(Figure 5.16). The opening should be framed to 10 in. x
10 in. (254mm x 254mm) inside dimensions, in the same
manner as shown in Figure 5.13, on the previous page.
Ceiling Firestop
Minimum 1 in.
(24mm) Clearance
Minimum 1 in.
(24mm) Clearance
Figure 5.16
Fire Risk.
Explosion Risk.
• Any occupied areas above the first floor, including
closets and storage spaces, which the vertical
vent passed through must be enclosed. The
enclosure may be framed and sheetrocked with
standard construction materials; however, refer
to these installation instructions for the minimum
allowable clearance between the outside of the
vent pipe and the combustible surfaces of the
enclosure. Do not fill any of the required air space
with insulation.
Page 18
Nails
Minimum 1 in.
(24mm) Clearance
Minimum 1 in.
(24mm) Clearance
WARNING
Heat & Glo · Tiara I B & Tiara II B · 7010-149L
November 14, 2007

Advertisement

Table of Contents
loading

Table of Contents