7.2
PROCEDURES FOR LP 33U Series PARALLEL SYSTEM
7.2.1 LP 33U Series Parallel System start-up
WARNING
Before connecting hazardous voltages, make sure that:
• The connection to the electrical system has been performed by qualified personnel;
• The equipment frame has been correctly grounded to the main earth;
• Make sure that utility input protection is removed;
• All the panels removed to allow the UPS connection have been correctly reinstalled;
• The UPS switches Q1 and Q2 are OFF (Pos. 0);
• The "battery breaker" Q3 is OFF.
This procedure must be performed for the first start-up following the installation, with all the UPS units
completely switched Off and not powered.
This procedure presupposes that the load is not yet supplied by the UPS Parallel System.
NOTE !
The UPS Parallel System can be started-up using the battery supply in case the input
utility should be unavailable.
To avoid an incidental battery discharge, it is recommended to proceed to the UPS
Parallel System start-up having the input utility available.
Open the front door on all UPS units and make sure that:
All the connections to the input/output terminals of the UPS have been made correctly.
•
The safety screens are fixed in their position.
•
The switches Q1 and Q2 are open (Pos. O) and the "battery breaker" Q3 is OFF..
•
Q1
UPS output switch
Q2
Manual bypass switch
Key
Inverter ON
Inverter OFF
Modifications reserved
OPM_LPS_3UO_50K_60K_1US_V010.doc
!
Key
Key
Total Off
LEDs on synoptic diagram
LED 1
Utility rectifier OK
LED 2
Utility bypass OK
LED 3
Rectifier ON
LED 4
Discharging battery
LED 5
Booster ON
LED 6
Charge battery ON
LED
LED
Stop Operation
Alarm
LED 7
Inverter available
LED 8
Inverter ON
LED 9
Q1 closed
LED 10
Automatic bypass ON
LED 11
Manual bypass Q2 ON
LED 12
Load on UPS
LED
Operation
Continue ►
Page 51/65