SlimFit
commercial condensing gas
Prepare boiler location
Placing multiple boilers
1. Locate multiple boilers in boiler room to
provide the clearances shown in:
a. Figure 4 (side-to-side), or
b. Figure 6 (mirror-image mounting).
c. Other layouts can be used if all re-
quired clearances are maintained.
2. Provide indicated clearances around
boilers for access and servicing. If rec-
Figure 4
Side-to-side mounting of multiple SlimFit boilers — LEFT-HAND boilers only
Figure 5
Side-to-side mounting of multiple SlimFit boilers — RIGHT-HAND boilers only
8
-
fired water boiler
(continued)
ommended dimensions are not possible,
provide at least the minimum clearances
given on page 7. Also follow local codes.
3. Construct boiler foundation if boiler
room floor is uneven or if there is a danger
of flooding. Size foundation to allow for
clearance and spacing dimensions shown
in either Figure 4 or Figure 6.
— Boiler Manual
Verify that boiler placement and clearances
comply with all applicable codes.
4. Chalk-line boiler locations on foundation
or boiler room floor.
5. Uncrate, assemble and mount boilers
according to instructions in this manual.
6. Provide clearance for installation of vent-
ing, air piping, gas piping, condensate
piping and components, expansion tank,
boiler pump and other accessories.