Hardware Options Installation
2. Insert the hot-plug SCSI hard drive. Be sure the drive seats firmly into the
connector on the SCSI backplane (1).
3. Close the ejector lever (2).
Figure 4-8: Installing a hot-plug SCSI hard drive
4. If you replaced a hard drive, restore the server blade data from the backup.
5. Use the hot-plug SCSI hard drive LEDs to identify the status of the installed
drive. For more information about LEDs, refer to "Hot-Plug SCSI Hard Drive" in
Chapter 1, "Server Blade Component Information."
6. Resume normal server blade operations.
4-8