Factory Installed Economizer; Temperature Limit Switch Usage For Electric; Heat Units; Horizontal Discharge Conversion - Trane TSC037E Installation, Operation And Maintenance Manual

Packaged rooftop air conditioners precedent - electric/electric 3–10tons–60hz
Table of Contents

Advertisement

Install and connect a condensate drain line to the
evaporator drain connection.

Factory Installed Economizer

Ensure the economizer has been pulled out into the
operating position. Refer to the economizer installers
guide for proper position and setup.
Install all access panels.
Temperature Limit Switch Usage for
Electric Heat Units
Units are factory shipped in the downflow discharge
configuration but can be field converted to a horizontal
discharge configuration. Some, but not all units require a
differentTCO-A limit switch, which is wire tied near the
terminal block in the heater compartment if horizontal
discharge configuration is used.

Horizontal Discharge Conversion

(3 Through 5 Ton Units)
Note: 3 - 5 ton units supply cover to supply opening and
return cover to return opening.
Supplies Needed by Installer for Conversion: 3 oz. tube of
HighTemperature RTV sealant. (500°F / 260°C: Similar to
Dow Corning 736)
Note: Failure to use recommended sealant could result in
unit performance loss.
If a unit is to be converted to a Horizontal discharge, the
following conversion must be performed:
1. Remove RETURN and SUPPLY duct covers.
2. Locate supply cover. Apply ¼ in. (6mm.) continuous
bead of 500°F RTV sealant to the flange as shown.
Figure 26. Supply duct cover
RTV Sealant
3. Position duct cover as shown, rotate 90 degrees to
allow entrance into supply opening.
4. Slide duct covers into duct openings until inward edge
of duct cover engages with the 2 retaining clips on the
duct flanges. Secure the outward edge of each duct
cover with 2 screws.
5. Slide RETURN DUCT COVER (insulation side up) into
supply opening until inward edge of duct cover
engages with the 2 retaining clips on the duct flange.
Secure outward edge of the duct cover with two
screws.
RT-SVX22M-EN
Note: Certain unit/electric heater combinations require a
limit switch change out for horizontal airflow
applications. Refer to the following instructions to
determine if this process is required for the unit
undergoing installation.
Horizontal Discharge Conversion
(6 Through 10 Ton Units)
Note: 6 - 10 ton units the supply cover to return opening
& return cover to supply opening.
Supplies Needed by Installer for Conversion: 3 oz. tube of
highTemperature RTV sealant. (500°F / 260°C: Similar to
Dow Corning 736)
Note: Failure to use recommended sealant could result in
unit performance loss.
If a unit is to be converted to a Horizontal discharge, the
following conversion must be performed:
1. Remove RETURN and SUPPLY duct covers.
2. Place SUPPLY DUCT COVER over down-flow return
opening. (insulation side down)
3. Using self-drilling screws, (or screws removed from
duct cover), screw through dimples to attach DUCT
COVER to base.
Figure 27.
Supply duct cover
Supply Duct Cover
Screw into 4
dimples on top
edge
4. On original RETURN DUCT COVER, apply ¼"(6mm.)
continuous bead of 500°F RTV sealant around flange
(opposite insulation side), as shown.
Figure 28. Return duct cover
RTV Sealant
5. Slide RETURN DUCT COVER (insulation side up) into
supply opening until inward edge of duct cover
engages with the 2 retaining clips on the duct flange.
Secure outward edge of the duct cover with two
screws.
Installation
27

Hide quick links:

Advertisement

Table of Contents
loading