Additional Corrosion Protection; Voltage Regulator Adjustment; Section 3 - Operation; Break-In Procedure - Generac Power Systems Guardian 04758-2 Installation And Owner's Manual

Guardian air-cooled automatic standby generator installation and owner's manual
Hide thumbs Also See for Guardian 04758-2:
Table of Contents

Advertisement

5. Remove load, stop engine, loosen the idle adjust
screw and reconnect the idle spring.
6. Using a hand, push the governor arm to the
closed throttle position. Make sure the idle spring
does not stretch at all.
7. Restart the unit.
8. Slowly turn the idle adjust screw to adjust the no-
load idle frequency to 63-63.5 Hz.
9. The governor is now set.
2.7.3
ADDITIONAL CORROSION
PROTECTION
Periodically spray all engine linkage parts and brack-
ets with corrosion inhibiting spray such as WD-40 or
a comparable product.
2.8
VOLTAGE REGULATOR
ADJUSTMENT
With the frequency between 62-63.5 Hertz, slowly
turn the slotted potentiometer (Figure 2.6) until line
voltage reads 244-252 volts.
Remove the access panel on top of the control
panel to adjust the voltage regulator.
Figure 2.6 – Voltage Adjustment Potentiometer
The voltage regulator is housed above the generator's
control panel. The regulator maintains a voltage in
direct proportion to frequency. For example, at 62
Hertz, line-to-neutral voltage will be 124 volts.
3.1

BREAK-IN PROCEDURE

Once the unit has been installed, with utility power
connected to the transfer switch, and all electrical
checks have been made, it is strongly recommended
that the following "Break-in Procedure" be completed
to ensure correct generator operation in the future.
14
Section 3 — Operation
Air-cooled 7 kW, 12 kW and 15 kW Generators
NOTE:
NOTE:
1. Set the generator's AUTO/OFF/MANUAL switch to
AUTO.
2. Turn OFF the utility power supply to the transfer
switch using the means provided (such as a utility
main line circuit breaker).
3. The unit will start, and the transfer switch will
transfer to standby.
4. Run the unit for one hour at 25 percent load.
5. Run the unit for one hour at 50 percent load.
6. Run the unit for one hour at 75 percent load.
7. Run the unit for one hour at 100 percent load.
8. Turn ON the utility power supply to the transfer
switch, which will allow the transfer switch to
transfer back to utility power. The unit will con-
tinue to run for one minute and then shut down.
9. Allow the unit to cool.
10. Drain the oil and remove the oil filter. Replace
the oil filter according to Section 4.4, "Changing
the Oil Filter". Replace the oil with synthetic oil
as recommended in Section 4.3, "Changing the
Engine Oil".
11. The generator is now ready for service.
3.2
USING THE AUTO/OFF/MANUAL
SWITCH (FIGURE 3.1)

3.2.1 "AUTO" POSITION

Selecting this switch position activates fully automatic
system operation. It also permits starting and exercising
the engine every seven days with the setting of the exer-
cise timer (see Section 3.6). This position also is used
for remote starting, when it is set up.

3.2.2 "OFF" POSITION

This switch position shuts down the engine. This
position also prevents automatic operation.

3.2.3 "MANUAL" POSITION

Set the switch to MANUAL to crank and start the
engine. Transfer to standby power will not occur
unless there is a utility failure.
Figure 3.1 – Generator Control Panel
FUSE
5A
AUTO
OFF
MAN.
FUSE
SET
15A
EXERCISE
TIME
R
L o c a t e y o u r n e a r e s t
d e a le r a t :
R
POWER SYSTEMS, INC.
SYSTEM SET
LOW OIL
HIGH TEMP.
OVER SPEED
OVER CRANK
F L A S H IN G G R E E N L E D =
N O U T IL IT Y
S E N S E
4
F L A S H IN G R E D L E D S =
E X E R C IS E R N O T S E T

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Guardian 04759-2Guardian 04760-2

Table of Contents