STEP 6 SECURE WIRING

• Route house wiring through the ceiling hole
and pull a length to reach the hood junction box,
approximately 6" below the support.
Support
Frames
• Tape the wire to the left side of the frame
538Dia20
support to prevent damage during installation
and service.
Installation Instructions
Ceiling
Left Side
View
Tape
House
Wiring
STEP 7 SIZE AND INSTALL
DUCTWORK
• Measure from house duct flange to bottom of support
frame (Dim. A).
– Add at least 1" for duct overlap at the top.
– Subtract 1-3/4" for hood insertion into the bottom
of the frame to determine required duct length.
• Cut the 8" duct length required.
NOTE: The bottom of the duct must be external
(female) connection to the top of the hood. The
bottom end should be flared slightly, to facilitate
installation of the hood.
• Install duct up through support frames and attach
to house ducting with sheet metal screws.
• Seal the connection with duct tape.