Filler Panel Installation; Installing Back Supply Plenum; Installing The Supply Duct Collar; Hanging The Back Supply Plenum - Greenheck Type I Installation, Operation And Maintenance Manual

Kitchen hoods
Table of Contents

Advertisement

Filler Panel Installation

1. Uncrate the hood and lay it on the floor with
protective material between the hood and the floor.
2. Bolt the filler panels together with 5/16 in. bolts
provided in the hardware package.
3. Position the filler panels to the hood back, and tack-
weld them into place.
TACK-WELDED TO
HOOD BACK
5/16 IN. X 3/4 IN. BOLTS
WITH WASHERS & NUTS
4. To allow for ease of cleaning, caulk the external
seams with NSF Approved silicone caulk (GE
SCS1009, or its equivalent). The caulk is not
provided.
Installing the Back Supply Plenum

Installing the Supply Duct Collar

1. Find the center of the back supply plenum.
2. If the back supply plenum is
to have one opening, cut the
opening such that it is centered
at L /2 from the plenum end.
(Fig. 1)
3. If the back supply plenum is to
have two openings, cut openings
such that they are centered
at L /4 from each end of the
plenum. (Fig. 2)
4. Place the duct collar(s) over the
opening(s), fastening with screws
or tack-welds
every 4 to 6 in.
(10.16 to 15.24
cm). (Fig. 3)
Fig. 3
®
HOOD
HOOD
HOOD
RIGHT FILLER PANEL
BOTTOM FILLER PANEL
Fig. 1
L (MODULE LENGTH)
L/2
L/2
Fig. 2
L (MODULE LENGTH)
L/4
L/2
L/4

Hanging the Back Supply Plenum

5. Hang the back supply plenum from the ceiling.
• The back supply plenum needs to be mounted
31.25 in. (79.375 cm) above the finished floor. This
is measured from the lowest rear edge of the back
supply plenum to the finished floor.
• Hang using threaded rod placed through the hanger
brackets.
6. Fasten the back supply to the wall, going through the
lower back supply wall.
• These fasteners are to help maintain the location of
the back supply, and are not intended to hold the
weight of the back supply unit.
• The fasteners should not interfere with the
removable air diffusers
FASTENERS HOLDING THE
BACKSUPPLY TO THE WALL

Hood Hanging Height

The hood hanging height is critical. Hanging the hood at
the incorrect height may significantly reduce the ability
of the hood to function properly and may be in violation
of codes. The hood hanging height, typically 78 in.
(198.12 cm) above the finished floor, is given on the
UL label located on the end panel on the inside of the
hood. The hood must be hung level to operate properly.
The grease trough is pitched to drain into the grease
container.
Kitchen Hoods • Type I and Type II
31.25 INCH
CRITICAL
DIMENSION
5

Advertisement

Table of Contents
loading

This manual is also suitable for:

Type ii