7
|
Installation
7.8.2 To close the outdoor unit
7.8.3 To check the insulation resistance of the compressor
Installer reference guide
64
d
c
a
b
g
a Gas pipe
b Gas pipe insulation
c Interconnection cable
d Field wiring (if applicable)
e Liquid pipe
f Liquid pipe insulation
g Finishing tape
2 Install the service cover.
2
NOTICE
If, after installation, refrigerant accumulates in the compressor, the insulation
resistance over the poles can drop, but if it is at least 1 MΩ, then the unit will not
break down.
▪
Use a 500 V mega-tester when measuring insulation.
▪
Do NOT use a mega-tester for low voltage circuits.
1 Measure the insulation resistance over the poles.
If
≥1 MΩ
<1 MΩ
2 Turn ON the power and leave it on for 6 hours.
Result: The compressor will heat up and evaporate any refrigerant in the
compressor.
3 Measure the insulation resistance again.
e
f
3
1×
Insulation resistance is OK. This procedure is
finished.
Insulation resistance is not OK. Go to the next step.
PH2
8 mm
Then
RZAG71~140N
Sky Air Alpha-series
4P695307-1A – 2024.02