Weeks
Responsibility
Before
Schedule
Delivery
Date
Customer
IBM
.;
Event
12
x
Arrange for the installation of ( 1
j
the device cables between the
3276 and the attached units
and (2) the power receptacles,
wiring, etc.
x
Define a training program for
employees.
x
Order the required 3276, 3278, 3279,
3287, and 3289 manuals.
10
x
Review the progress of the data
communication plan. Identify
and resolve any schedule conflicts.
9
x
x
Review the cluster configuration
to make sure the configuration
meets your requirements. Make
any necessary changes to your
order.
8
x
x
Review the installation plan to
define any exposure to schedule.
x
x
Confirm the arrival of package
containing cluster cables.
x
Start installing and labeling cluster
cables and power receptacles.
6
x
Start employee training.
x
I BM representative checks progress
of site preparation.
4
x
Receive supplies (magnetic
stripe cards, forms, etc.).
x
Complete the installation of cables
and power receptacles.
2
x
Complete the checkout of the
cables and power: continuity and
polarity tests of cluster cables,
power receptacles, and safety
considerations.
x
Complete the required changes to
the existing programs and data
processing units.
x
Complete the site preparation.
x
Install communication facilities
(telephone line and modems).
x
Make sure all the necessary
information is available for the
setup personnel (switch settings,
configuration information,
customizing form, etc.).
x
Review setup instructions with the
setup personnel.
Figure A-1 (Part 2 of 3). Planning Checklist, Sample Plan