Commissioning, inspection, maintenance
Checking the DHW expansion vessel (if installed) and pre-charge pressure
Fig. 37
1. Check the static pressure of the DHW line down-
stream of the pressure reducer and adjust if
required. Set value: Max. 3.0 bar (0.3 MPa)
2. Close the on-site shut-off valve in the cold water
line.
3. Turn levers on valves
position.
4. Close cold water supply
Checking the safety valve function
56
B
C
D
A
A
and
B
to the "right-hand"
.
C
E
5. Drain the pipe via air vent valve
6. Check the pre-charge pressure of DHW expansion
vessel
and adjust if necessary. Set value: Static
E
pressure minus 0.2 bar (20 kPa)
7. Return the levers of valves
position. Open cold water supply
site shut-off valve in the cold water line.
D
.
A
and
B
to the "top"
and the on-