Activating Screed Drying; Leak Test On Balanced Flue System (Annular Gap Check) - Viessmann VITODENS 111-W Installation And Service Instructions Manual

Table of Contents

Advertisement

Adjusting pump rate of integral circulation pump
Curve
A
B
C
D
E

Activating screed drying

Screed drying
Six different temperature profiles can be set for screed
drying:
Default temperature profiles can be set in "System
configuration".
For further details, see "Function description".

Leak test on balanced flue system (annular gap check)

A
Fig. 28
A
Combustion air aperture
For balanced flue systems tested together with the
heat generator, there is no requirement for a tightness
test (overpressure test) during commissioning by the
flue gas inspector.
In this case, we recommend that a simple tightness
test is carried out during system commissioning. For
this, check the CO
or O
2
2
tion air at the annular gap of the balanced flue pipe.
If the CO
concentration is less than 0.2 % or the O
2
concentration is greater than 20.6 %, the flue pipe is
deemed to be sufficiently gas-tight.
Pump rate of circulation pump
concentration in the combus-
2
Commissioning, inspection, maintenance
(cont.)
Note
Screed drying applies to all connected heating circuits
simultaneously! DHW heating is not possible during
screed drying.
If actual CO
values are greater or O
2
then pressure test the flue pipe with a static pressure
of 200 Pa.
!
Please note
If the test port is not sealed, combustion air is
drawn in from the room.
After the tightness test, re-seal the test port with
the plug.
60 %
70 %
80 %
90 %
100 %
values are lower,
2
47