Figure 9. Release latches and server
4. Remove the shipping bracket that is on the left side of the rear of the system before you cable it. To
remove the shipping bracket, complete the following steps:
a. Remove the two screws (A), as shown in Figure 10.
Figure 10. Shipping bracket removal
b. Pull the bracket off of the system (B) and discard.
c. Push the power supplies back into the system, ensuring that they are fully seated and latched.

Installing the cable-management arm

Use the procedure in this task to install the cable-management arm.
Installing the server into a rack