Figure 1. Removing the filler panels

Marking the location

You might need to mark the installation location. Use this procedure to perform this task.
To mark the installation location and install the nut clips into a rack, complete the following steps:
1. Facing the front of the rack and working from the right side, locate the bottom EIA unit that your
system will use. Make a note of the EIA location. Use tape, a marker, or a pencil to mark the bottom
hole of this EIA unit as A. Mark the rack so that the mark can also be seen from the rear of the rack,
as shown in Figure 2 on page 5.