Installing The Cable-Management Arm - IBM Power 730 Express Manual

Hide thumbs Also See for Power 730 Express:
Table of Contents

Advertisement

Figure 9. Release latches and server
4. Remove the shipping bracket that is on the left side of the rear of the system before you cable it, as
shown in Figure 10. To remove the shipping bracket, complete the following steps:
a. Remove the two screws (A).
Figure 10. Shipping bracket removal
b. Pull the bracket off of the system (B) and discard.
c. Push the power supplies back into the system, ensuring that they are fully seated and latched.
5. Continue with "Installing the cable-management arm."

Installing the cable-management arm

You might need to install the cable-management arm. Use this procedure to perform this task.
To install the cable-management arm, complete the following steps:
Installing the server into a rack
9

Advertisement

Table of Contents
loading

This manual is also suitable for:

Power 710 express8231-e1c8231-e2c

Table of Contents