After Installation; Air Purge - LG JB-Q66LRA0 Installation Manual

Table of Contents

Advertisement

After Installation

Air Purge

Air Purge of the Connecting
Pipes and the Indoor Unit
The air which contains moisture remaining in the
refrigeration cycle may cause a malfunction on the
compressor.
1
Confirm that both the liquid side valve and the
gas side valve are set to the closed position.
2
After connecting the piping, check the joints for
gas leakage with gas leak detector.
3
Remove the service port nut, and connect the
gauge manifold and the vacuum pump to the
service port by the charge hose.
4
Vacuum the indoor unit and the connecting
pipes until the pressure in them lowers to
below 76 cmHg.
5
Remove the valve stem nuts, and fully open the
stems of the 2-way and 3-way valves with a
hexagon wrench.
6
Tighten the valve stem nuts of the 2-way valve
and 3-way valve.
After Installation
7
Disconnect the charge hose and fit the nut to
the service port. (Tightening torque: 1.8 kg.m)
25