Table of Contents

Advertisement

Installation

Foundation
Complete
foundations are suitable or strip
foundations may also be used (see
When selecting and preparing the unit
Figure 7).
site, follow these guidelines:
In the case of strip foundations,
concrete or steel supports are
1.Ensure that the site can support the
premissible, but support is required
total weight of the unit. Unit weight
under breakpoints and every 2 m along
figures only provide total gross
the unit base.
weights and do not include the
Additional weight for water in any
coils.
2.Confirm that the foundation of the
mounting platform is large enough to
Include the unit dimensions plus
service plus service access.
3.The floor or foundation must be level
for correct coil drainage and
condensate flow.
4.Provide adequate lighting for
maintenance personnel to perform
maintenance duties.
5.When the unit is positioned on site,
there must be sufficient space
around the unit to ensure that correct
operation and effective main-
tenance can be carried out. Figure 6
gives recommended space
allowances.
●On the designated access side of
the unit, working areas must have
minimum 1 mtr, space (P).
●Allowance for coil connections,
dimension"C" must be dimension
200mm + unit width.
●A clear unobstructed area before
and after an air intake or discharge
is required to ensure correct air
movement. The width of the area
must be >= the width of the unit, and
the depth (dimension "L")must be
>= 0.5 x the overall unit height.
6
reinforced
concrete
C
P
L
P = 1 MTR min
Figure 6
BREAKPOINT
2m
2m
Figure 7 - Air Handling Unit Steels Foundation
Installation
IMPORTANT
FAILURE TO PROVIDE A LEVEL
PLINTH OR SUPPORT WILL
RESULT IN DOORS JAMMING
AND AIR LEAKS FROM THE
CASING.
Erection
To minimize noise transmission,
insulation material such as cork
slabbing (TICO pads) or rubber pad
May be placed between the unit base
Figure 8 - Air Handling Unit Plinth Foundation
and the foundation (see Figure 8).