Step 3: (Gas Dryer Only) Connect Gas
Supply Pipe
WARNING
To reduce the risk of gas leaks, fire or
explosion:
• The dryer must be connected to the type
of gas as shown on nameplate located in
the door recess.
• Use a new flexible stainless steel
connector.
• Use pipe joint compound insoluble in L.P.
(Liquified Petroleum) Gas, or Teflon tape,
on all pipe threads.
• Purge air and sediment from gas supply
line before connecting it to the dryer.
Before tightening the connection, purge
remaining air from gas line to dryer until
odor of gas is detected. This step is
required to prevent gas valve
contamination.
• Do not use an open flame to check for gas
leaks. Use a non-corrosive leak detection
fluid.
• Any disassembly requiring the use of
tools must be performed by a suitably
qualified service person.
1. Make certain your dryer is equipped for use with
the type of gas in your laundry room. Dryer is
equipped at the factory for Natural Gas with a
3/8 inch NPT gas connection.
NOTE: The gas service to a gas dryer must
conform with the local codes and ordinances, or in
the absence of local codes and ordinances, with the
latest edition of the National Fuel Gas Code ANSI
Z223.1/NFPA 54 or the CAN/CGA-B149, National
Gas Installation Code.
Natural Gas, 1000 Btu/ft
be supplied at 6.5 ± 1.5 inch water column pressure.
For proper operation at altitudes above 3000 feet
(915 m) the natural gas valve spud orifice size must be
reduced to ensure complete combustion. Refer to
Table 2.
8
3
3
(37.3 MJ/m
) service must
© Copyright, Alliance Laundry Systems LLC – DO NOT COPY or TRANSMIT
Natural Gas Altitude Adjustments
Altitude
feet
m
3000
915
6000
1830
8000
2440
9000
2740
10,000
3050
2. Remove the shipping cap from the gas
connection at the rear of the dryer. Make sure you
do not damage the pipe threads when removing
the cap.
3. Connect to gas supply pipe.
NOTE: When connecting to a gas line, an
equipment shut-off valve must be installed within
6 feet (1.8 m) of the dryer. An 1/8 in. NPT pipe plug
must be installed as shown for checking inlet
pressure. Refer to Figure 5.
1
W316
1
New stainless steel flexible connector -
(Use design CSA certified connector)
Use only if allowed by local codes
2
1/8 in. NPT Pipe Plug
3
Equipment Shut-Off Valve
4
Black Iron Pipe Shorter than 20 ft. (6.1 m) -
Use 3/8 in. (9.5 mm) pipe
5
3/8 in. NPT Gas Connection
Orifice Size
No.
inches
mm
43
0.0890
2.26
44
0.0860
2.18
45
0.0820
2.08
46
0.0810
2.06
47
0.0785
1.99
Table 2
5
4
Figure 5
Part No.
503778
58719
503779
503780
503781
2
3
D233I
D699I
512100

Advertisement

Table of Contents
loading

This manual is also suitable for:

Cgs68awf

Table of Contents