Commissioning
5.5 Differential pressure and flow rate
5. Open the shut-off valve
6. Open the shut-off valve for the process
5.5
Differential pressure and flow rate
Incorrect or improper operation
If the lock screws are missing or are not sufficiently tight, and/or if the valves are operated
incorrectly or improperly, it could lead to serious physical injuries or considerable damage to
property.
Measure
● Make sure that the lock screws and/or the vent valve are screwed in and fully tightened.
● Operate the valves properly.
5.5.1
Commissioning in gaseous environments
Requirement
All shut-off valves are closed.
42
⑥
WARNING
at the pressure tapping point.