Requirements for the site

The installation location must fulfil the following requirements:
 The installation will be executed within a building.
 The BEKOKAT
®
 The ambient temperature must not exceed the specifications on the rating plate.
 Select a level, solid and vibration-free installation surface with a maximum inclination of
< 5% to all sides. The weight of the BEKOKAT
selecting the surface.
 Set up the converter so that the system is easily accessible from the sides and from the
top.
 Ensure adequate ventilation and heat dissipation.
 Maintain a safe distance to traffic routes when setting up the BEKOKAT
 The blow-off direction of the safety valve must be away from traffic routes. An
appropriate risk assessment must be carried out at the installation site.
 Equip the system with suitable collision protection.
 Ensure that no water or condensate can ingress into the BEKOKAT
 Install an easily accessible manual shut-off valve before and after the assembly unit.
 The surrounding area must be free of aggressive, corrosive, caustic, toxic, flammable
or oxidising substances.
 The intake area of the compressor must be free of aggressive, corrosive, caustic, toxic,
flammable or oxidising substances.
V01 /11-038
must be protected from exposure to moisture.