SICHARGE UC MastHood

5.4 Commissioning

5.4
Commissioning
Note
Take into consideration the steps in the charger's commissioning log to complete the
installation
Commissioning
No.
1
Measure and write down the following values before the first power on:
Voltage level
Earth loop impedance
Insulation resistance
2
Switch on the following switch elements on the SICHARGE UC charging station for the low voltage
cable/AC of the SICHARGE UC MastHood
Backup fuse
Residual current operated circuit breaker
MastHood MCB if necessary
3
Measure and write down the following values:
Voltage AC
In manual mode or resistance and continuity measurement
Voltage DC
DC polarity on the DC contactors
DC polarity on the contact hood
Check CP signal and PE
4
Wait until the SIMATIC S7-1200 CPU of the SICHARGE UC MastHood has fully started
5
Flash S7 with SICHARGE-UC-cascade SW (If with linux board instead of S7 then N/A)
6
In case the Masthood S7-1200 (CPU 1214C DC/DC/DC 6ES7 214-1AG40-0XB0) is different from the
one in the project (CPU 1214C DC/DC/Rly 6ES7 214-1HG40-0XB0), the device must be changed in
the HW Config of the S7
7
For use with MastHood, first go to Device Configuration (HW Config) and remove the AIxRTD card
used to measure the plug temperatures.
8
Flash the AKKA with the latest Software.
9
After the checking the SICHARGE UC MastHood, mount the plastic cover
10
Close the maintenance door
11
Initiate charging session with EV for verification
Initialize the Log
No.
1
Start a log file from the V2G communication
2
Log will start
52
Checklist item
Checklist item
Installation and Commissioning Checklist for SICHARGE UC
Product Information, 03/2023, A5E52548271-AA
P
F
N/A
P
F
N/A

Advertisement

Table of Contents
loading

Table of Contents