Control (annually)
Customer:
Serial number:
Location:
-
Checking delivery
No.
1
Check the completeness of the delivery
2
Check that the delivery documents correspond to the goods delivered
Checking the shock indicator
No.
1
Check whether there is a shock indicator on the transport packaging
2
Check the serial number of the shock indicator for manipulation
3
Check whether the glass tube in the middle of the indicator has turned red
4
Report any red colored or missing indicator to the carrier immediately
5
Check the incoming goods with the visual inspection of the overall transport packaging
6
Take pictures of the dispenser while still in the transport package
7
Check if the equipment has the factory report and attach the original to the report
Installation and Commissioning Checklist for SICHARGE UC
Product Information, 03/2023, A5E52548271-AA
Date:
Date of manufacture:
Name:
-
Checklist item
Checklist item
4
P
F
N/A
P
F