automatically return to standby mode.
8. If prime is not established during the
four minute pump prime mode, return
to step 5 to re-enter Pump Prime
mode. Repeat steps 5 through 7
until the pump is fully primed and the
oil is free of bubbles.
9. Terminate the call for heat, and the
control will resume normal operation.

Cad Cell Resistance Measurement

The Beckett 7575 control cad cell
resistance can be selected and read
on the GeniSys Contractor Tool, part
52082U.
If the contractor tool is not available, the
cad cell leads can be unplugged from the
control and the resistance measured with
a meter in the conventional way.
Conduct these tests with flame present.
Flame Detection Range
Normal (0 - 1600 ohms)
Limited (1600 ohms to lockout)
Resetting From Restricted or
Hard Lockout
Before starting or resetting the
control from restricted lockout
state, troubleshoot the heating
system for the root cause(s) of
the lockout.
Make necessary repairs or adjustment to
ensure a safe start condition.
Ensure that the appliance is free of oil and oil
vapors before starting or resetting the burner.
If the control continues to lock out
without a satisfied call for heat, or
fails the motor relay check, the control
enters Hard (restricted) Lockout in order
to limit accumulation of unburned oil in
the combustion chamber.
120v GeniSys Control Installation and Operation Manual
Fire & Smoke
Hazard
To reset, hold the button down for 15
seconds until the red light turns off and
the yellow light turns on.
Always verify the control functions
according to all specifications before
leaving the installation site.
Replace the control if it does not
operate as specified.

Disable Function

Any time the burner is running, press
and hold the reset button to disable the
burner. The burner will remain off as
long as the button is held.

Maintenance

Oil heating systems require annual
service performed by a qualified,
professional service agency. The 7575
primary control should be inspected
during this service routine according to
the following checklist:
NOTE: The 7575 control has no
serviceable internal parts.
Inspect the exterior of the control.
Replace the control if there is any
sign of impact damage, prolonged
exposure to water, or corrosion.
Use a multimeter to test the line
voltage at control L1 and L2. It
should be 102 - 132 Vac.
Inspect all external wiring for secure
connections and verify insulation
integrity.
Verify the control lockout and
operation sequence, (Reference
Startup/Checkout section).
Observe a full operating cycle to
prove the sequence and timings are
correct.
Replace any control that does not
meet listed specifications with an
equivalent replacement unit.
11

Advertisement

Table of Contents
loading

This manual is also suitable for:

7575a00007575p15157575p054m

Table of Contents