5 - 2
•
The system must be switched on during the measurement. Measuring instruments with
automated measuring sequences must therefore be set to manual measurement.
•
Enter the highest value as first measured value in the report 'Device leakage current /
report' (chapter 7 of these instructions).
•
This value must not exceed the permissible leakage current values of 2.5 mA according
to DIN VDE 0751-1:2001-10, Table F.1, line "Device leakage current for devices
according to remarks 1 and 3".
•
Transfer the current line voltage from the 'Start-up report' into the report 'Device leakage
current / report'. If the current line voltage deviates from the nominal voltage, then correct
the measured value to the value corresponding to a measurement at the nominal value
of the line voltage. Document this in addition.
•
Document the measuring procedure (differential measurement or direct measurement)
and the measuring instrument used (designation and serial number).
Reports
•
Separate the completed 'Start-up report' (chapter 6 of these instructions) from these
instructions and file it in the system folder, "Certificates" register.
•
Separate the completed reports 'Protective conductor resistance / report' and
'Device leakage current / report' (chapter 7 of these instructions) from these instructions
and file them in the system folder , "Certificates" register.
•
Complete the 'Installation Protocol' located on the system and send it (per fax) to the
address stated in the protocol.
Last work steps
•
Wind the power connection cable onto the cable holder on the back of the control
console.
•
Lock the support arm in the traveling position (Fig. 1) and check the forced locking of the
support arm.
POLYMOBIL III
RXB8-115.034.02
Rev. 03
04.05
Final work steps
Page 2 of 2