Reports; Last Work Steps - Siemens POLYMOBIL III Start-Up Instructions

Hide thumbs Also See for POLYMOBIL III:
Table of Contents

Advertisement

5 - 2
The system must be switched on during the measurement. Measuring instruments with
automated measuring sequences must therefore be set to manual measurement.
Enter the highest value as first measured value in the report 'Device leakage current /
report' (chapter 7 of these instructions).
This value must not exceed the permissible leakage current values of 2.5 mA according
to DIN VDE 0751-1:2001-10, Table F.1, line "Device leakage current for devices
according to remarks 1 and 3".
Transfer the current line voltage from the 'Start-up report' into the report 'Device leakage
current / report'. If the current line voltage deviates from the nominal voltage, then correct
the measured value to the value corresponding to a measurement at the nominal value
of the line voltage. Document this in addition.
Document the measuring procedure (differential measurement or direct measurement)
and the measuring instrument used (designation and serial number).

Reports

Separate the completed 'Start-up report' (chapter 6 of these instructions) from these
instructions and file it in the system folder, "Certificates" register.
Separate the completed reports 'Protective conductor resistance / report' and
'Device leakage current / report' (chapter 7 of these instructions) from these instructions
and file them in the system folder , "Certificates" register.
Complete the 'Installation Protocol' located on the system and send it (per fax) to the
address stated in the protocol.

Last work steps

Wind the power connection cable onto the cable holder on the back of the control
console.
Lock the support arm in the traveling position (Fig. 1) and check the forced locking of the
support arm.
POLYMOBIL III
RXB8-115.034.02
Rev. 03
04.05
Final work steps
Page 2 of 2