Installation and start-up

Note
Because the Rosemount 700XA is available in different configurations, it is possible that
not all of the instructions in this section apply to your particular gas chromatograph (GC).
In most cases, however, to install and set up a Rosemount 700XA, Emerson recommends
that you follow the instructions in the same order as they are presented in this manual.
4.1

Installation considerations

Before installing the gas chromatograph (GC):
1.
2. Ensure that the connections to the enclosure meet local standards.
3. Use approved seals: either cable glands or conduit seals.
4. Remove any packing materials before powering up the GC.
5.
6.
Related information

Mounting arrangements

4.2
Mounting arrangements
The Rosemount 700XA can be installed in one of the following mounting arrangements:
Rosemount 700XA
WARNING
The GC is heavy and has a high potential of injuring personnel or damaging
equipment.
Anchor the GC solidly before making electrical connections.
Until all bolts are tight, ensure that the GC is supported to prevent unforeseen
accidents.
a. Install conduit seals within 3 in (76 mm) of the enclosure.
b. Seal unused openings with approved blanks (plugs). Threads for these
openings are M32 x 1.5.
WARNING
Hazardous area explosion hazard
Failure to follow this warning may result in injury or death to personnel.
Do not use a personal computer (PC) or printer in a hazardous area.
Emerson provides serial and Ethernet communication links to connect the
analyzer to the PC and to connect to other computers and printers in a safe area.