Download Print this page

Central Machinery 33497 Owner's Manual & Safety Instructions page 6

12 ton shop press

Advertisement

Hang the Bottle Jack
1. Hang the Springs (4) on the bars of
the Upper Beam. See Figure F.
2. Place the Bottle Jack (5) on the
center of the Jack Plate.
3. Slide the Jack Plate up the Frame Posts so
the Bottle Jack Saddle fits in the bracket on
the center underside of the Upper Beam.
Mounting to the Floor
1. With assistance, move the Shop Press to the
location where it is to be mounted. If needed, drill
four 1/2" diameter mounting holes in the Base
Supports and use as a template to mark the spots
where four 1/2" diameter holes will be drilled in the
concrete or wood floor. Check for any hidden wiring
or cables and adjust the location for the holes as
needed. Then, temporarily set the Shop Press aside.
2. For concrete floors use a masonry drill bit
to drill the four 1/2" diameter holes
(about 3"–4" deep) into the concrete.
Make sure to blow out the concrete dust
from the drilled holes. Insert lag screw
anchors (not included) into the holes.
Page 6
For technical questions, please call 1-888-866-5797.
4. Hook the Springs into the Eye Bolts (6) on the Jack
Plate to secure the Bottle Jack/Jack Plate in place.
Upper Beam (1)
Springs (4)
Springs (4)
Eye Bolts (6)
Figure F
3. Move the Shop Press back to the location where it
is to be mounted, and align the four 1/2" diameter
mounting holes in the Base Supports with the four
pre-drilled 1/2" holes in the concrete or wood.
Use four minimum 3" long, 1/2" diameter concrete
anchor bolts or lag bolts (not included) to secure
the Shop Press to the concrete or wood floor.
Bottle
Jack
(5)
Jack
Plate
(7)
Item 33497

Advertisement

loading