Gas connection

A
Fig. 9
1. Seal gas shut-off valve
Information on operation with LPG
Install an external safety solenoid valve if the boiler
is installed below ground level.
2. Carry out a tightness test.
Note
Only use suitable and approved leak detection
agents (EN 14291) and devices for the tightness
test. Leak detection agents with unsuitable constit-
uents (e.g. nitrides, sulphides) can cause material
damage.
Remove leak detection agent residues after test-
ing.
!
Please note
Excessive test pressure will damage the
boiler and the gas train.
Max. test pressure 150 mbar (15 kPa). If a
higher pressure is required for tightness
tests, disconnect the boiler and the gas train
from the main supply pipe (undo the fitting).
A
A
to the gas connection.
A
3. Purge the gas line.
Installing the boiler