Required Ssrs And Roles; Estimated Service Time; Required Tools; Prerequisites For This Procedure - IBM Power775 Service Procedure

Disk enclosure chassis service procedure
Hide thumbs Also See for Power775:
Table of Contents

Advertisement

2.7

Required SSRs and Roles

This service procedure requires two SSRs.
This service procedure contains steps to be performed by a customer system administrator and an IBM SSR
(System Service Representative).
The customer system administrator performs the STEPs in Sections marked with "<= CUSTOMER
TASK"
The SSR performs the STEPs in Sections marked with "<= SSR TASK"
2.8

Estimated Service Time

The time required to unpack a new chassis, change out a DE chassis and package the damaged chassis to be
shipped back to IBM is about 4 hours.

2.9 Required Tools

Service card (shipped in the Power 775 frame)
Fill and Drain Tool P/N 45D6928.
Cable Assembly, HPIC tool P/N 45D7998 (shipped in Power 775 Fill & Drain Tool Kit)
Cable Assembly E/Net (test tool) P/N 45D8000 (shipped in Power 775 Fill & Drain Tool Kit)
Lift Tool Kit 74Y1087
Ladder PN 46G5947 may be required for upper DE locations (shipped in the Power 775 Lift Tool
Kit)
Hand Tool Kit P/N 74Y0988
Torque Clutch P/N 74Y0985 (shipped in the Hand Tool Kit)
Ratchet handle P/N 6428240 (shipped in the Hand Tool Kit)
Extension (18") P/N 46K2707 (shipped in the Hand Tool Kit)
2 mm Hex Torque Driver P/N 74Y0983 (shipped in the Hand Tool Kit)
3 mm Hex Torque Driver P/N 74Y0998 (shipped in the Hand Tool Kit)
4mm Hex Torque Driver PN 41V1059 (shipped in the Hand Tool Kit)
5 mm Hex tool P/N 74Y0986 (shipped in the Hand Tool Kit)
10 mm Socket P/N 02F3582 (shipped in the Hand Tool Kit)
2.10

Prerequisites for this Procedure

In order to perform this procedure, you will need the following information:
1) The location code of the DE to be serviced.
2) The frame number and frame serial number of the DE to be serviced.
Power775 Disk Enclosure Chassis Service Procedure