Heating Connection; Transportation; Mounting - IVT LATENTO 500 Mounting Instruction

Unpressurized buffer storage tank
Table of Contents

Advertisement

Available languages

Available languages

5.1 Heating connection

It is essential to take care of professional bleeding (e.g. automatic bleeder) when
connecting the LATENTO 500 to the heat generator/s.

5.2 Transportation

Note
The LATENTO 500 may be tilted max. horizontally for a short time, e.g. when car-
rying it to the place of installation. Great care must be taken that the cover was
closed with all four clamps.

5.3 Mounting

Heed the following points when selecting the installation site for the LATENTO
500:
Frost-protected room.
Level, clean swept floor.
do not subject the LATENTO 500 to direct solar radiation
(the UV can destroy the plastic).
Heed the load capacity of the foundation, the filled LATENTO 500 weighs
approx. 580 Kg.
Keeping heat losses as little as can be, place the LATENTO 500 in the vicinity of
the reheating heat generator
If possible, mount system in a heated room to minimize heat losses
(EnEV – Energy Saving Decree)
20
The LATENTO 500 must always be delivered in a standing
position so as to avoid any damage.