INSTALLATION INSTRUCTIONS

WALL MOUNTING INFORMATION

1. Two holes, for the supply and return air openings,
must be cut through the wall as shown in Figure 3.
2. On wood-frame walls, the wall construction must
be strong and rigid enough to carry the weight of the
unit without transmitting any unit vibration. See
Figures 4 and 5.
WARNING
Fire hazard can result if 1/4 inch clearance to
combustible materials for supply air duct is
not maintained. See Figure 3.
3. Concrete block walls must be thoroughly inspected
to insure that they are capable of carrying the weight
of the installing unit. See Figure 4.

MOUNTING THE UNIT

1. These units are secured by wall mounting brackets
which secure the unit to the outside wall surface at
both sides. A bottom mounting bracket is provided
for ease of installation.
2. The unit itself is suitable for "0" inch clearance, but
the supply air duct flange and the first 3 feet of
supply air duct require a minimum of 1/4 inch
clearance to combustible material. If a combustible
wall, use a minimum of 30-1/2" x 10-1/2"
dimensions for sizing. However, it is generally
recommended that a 1-inch clearance is used for ease
of installation and maintaining the required
clearance to combustible material. The supply air
opening would then be 32" x 12". See Figures 2, 3
and 6 for details.
WARNING
Failure to provide the 1/4 inch clearance
between the supply duct and a combustible
surface for the first 3 feet of duct can result in
fire.
Manual 2100-526E
Page
8 of 24
3. Locate and mark lag bolt locations and bottom
mounting bracket location. See Figure 4.
4. Mount bottom mounting bracket.
5. Hook top rain flashing under back bend of top. Top
rain flashing is shipped secured to the right side of
the back.
6. Position unit in opening and secure with 5/16 lag
bolts; use 7/8 inch diameter flat washers on the lag
bolts.
7. Secure rain flashing to wall and caulk across entire
length of top. See Figure 2.
8. For additional mounting rigidity, the return air and
supply air frames or collars can be drilled and
screwed or welded to the structural wall itself
(depending upon wall construction). Be sure to
observe required clearance if combustible wall.
9. On side-by-side installations, maintain a minimum
of 20 inches clearance on right side to allow access
to heat strips and control panel and to allow proper
airflow to the outdoor coil. Additional clearance
may be required to meet local or national codes.

TYPICAL INSTALLATIONS

See Figure 5 for common ways to install the wall mount
unit.
WIRING — MAIN POWER
Refer to the unit rating plate for wire sizing information
and maximum fuse or "HACR" type circuit breaker size.
Each outdoor unit is marked with a "Minimum Circuit
Ampacity". This means that the field wiring used must
be sized to carry that amount of current. Depending on
the installed KW of electric heat, there may be two field
power circuits required. If this is the case, the unit serial
plate will so indicate. All models are suitable only for
connection with copper wire. Each unit and/or wiring
diagram will be marked "Use Copper Conductors Only".
These instructions must be adhered to. Refer to the
National Electrical Code (NEC) for complete current
carrying capacity data on the various insulation grades
of wiring material. All wiring must conform to NEC
and all local codes.
The electrical data lists fuse and wire sizes (75ºC
copper) for all models, including the most commonly
used heater sizes. Also shown are the number of field
power circuits required for the various models with
heaters.