3 Operating the Ethernet CP with
3.1

How to Commission an Ethernet CP

The essential steps in commissioning an Ethernet CP are shown in the following
overview:
Notice
The chart below shows the basic steps. Please read the device-specific
instructions in "Installation and Commissioning" in the description of your CP
(Manual Part B).
Installation and Commissioning
S7 - 300 / 400
Install the CP on the S7 standard rail
(S7-300) or in the S7 rack (S7-400).
Connect the power supply.
Connect the CP to Industrial Ethernet.
Turn on the S7 station.
A -58
Configuring / Programming
Install the STEP 7 configuration
software on a PG/PC.
Configure the Ethernet CP:
S
by configuring in the
project engineering
see Section 3.3
or
S
by programming
see Section6
Download the configuration data and the user programs to
the S7 station and/or CP.
Use the diagnostic functions during commissioning
and to analyze problems.