Installation
Wiring
knockouts (6)
(must be
located on
left side)
Drywall or sheetrock
FIG. 17
CB-TP5 rough-in box components
Remember that when mounting this rough-in box, the NXD mounting tabs must lie
flush against the outside of the sheetrock.
4. Thread the incoming power, RJ-45 audio/video, Ethernet, and USB wiring through the knockouts
(use of the left wiring knockouts are recommended with this installation).
Leave enough slack in the wiring to accommodate any re-positioning of the panel.
5. Install the drywall/sheetrock before inserting the main NXD unit into the CB-TP5.
Installation of an NXD Touch Panel
The NXD-CV5 can be installed either directly into the (optional) CB-TP5 or other solid surface
environment using the two different mounting options: drywall clips or solid surface screws. The
following sections describe mounting the touch panel directly into a pre-wall rough-in box, a solid
surface or drywall, and optional NXA-RK5 Rack Mount Kit.
Installing the NXD panel within a Rough-In Box
The rough-in box must be mounted prior to continuing this section. Refer to the procedures in the
Pre-Wall Installation of the Rough-In Box section on page 19 for detailed pre-wall installation
instructions. Verify that all necessary cables have been threaded through the knockouts on the left of the
rough-in box and the connections have been tested prior to installation of the NXD-CV5.
1. Remove the Faceplate/bezel (A in FIG. 18) from the main NXD unit (B in FIG. 18) by gripping the
faceplate and pulling with gentle outward force.
2. Verify the incoming power, RJ-45 audio/video, Ethernet, and USB cables have been properly
threaded through the wiring knockouts on the left of the rough-in box. Leave enough slack in the
wiring to accommodate any re-positioning of the panel.
20
Stud Mounting tabs
Stud
NXD Mounting tabs
(should lie flush against
the outside of the wall)
5" Modero Widescreen Touch Panel