HANDLING PAYLOAD METER

ATTACHMENTS AND OPTIONS
HANDLING PAYLOAD METER

OUTLINE OF SYSTEM

The payload meter performs statistical processing to calculate the payload by the signals received from the sus-
pension pressure sensors and clinometer, etc.
Also, it displays the calculated payload on the machine monitor and indicates the loading state with the external
display lamps.
You can download the data saved in the payload meter to a personal computer by using the special software (if
equipped).
Maintain the road surface, smoothly accelerate, and smoothly apply the brake. Otherwise, the roughness of the
road surface, sudden acceleration, and abrupt braking deteriorate the accuracy of the calculation.
Although the following functions are provided, you do not need to change them for the standard operation. If
setting is required, ask your Komatsu distributor.
Setting of Loading End Travel Dist
The payload meter judges that loading is completed when the machine travels continuously 160 m from the
loading pit.
If a dumping is performed before the machine travels continuously 160 m, the payload meter cannot recognize
the dumping. In this case, the cycle data may not be recorded correctly.
Setting of loading end travel distance is used to change the loading end travel distance when the distance be-
tween the loading pit and dumping pit is very short.
Display section of payload
While the machine monitor displays the standard screen, the
payload is displayed as shown in the figure.
6-2