4 Shipment and on-site trans-
port
The work described in this section is only to
be performed by personnel qualified for the
assignment accordingly.
4.1 Accepting the delivered
goods
After receiving the shipment, proceed as fol-
lows:
1. Check the scope of delivery. Check that
the specifications on the regulator name-
plate match the specifications in the de-
livery note. See the 'Markings on the de-
vice' section for nameplate details.
2. Check the shipment for transportation
damage. Report any damage to
SAMSON and the forwarding agent
(refer to delivery note).
3. Determine the weight and dimensions of
the units to be lifted and transported in
order to select the appropriate lifting
equipment and lifting accessories. Refer
to the transport documents and the 'De-
sign and principle of operation' section.
EB 2551-1 EN

Shipment and on-site transport

4.2 Removing the packaging
from the regulator
The tested regulator is delivered as an as-
sembled unit.
Proceed as follows to lift and install the regu-
lator:
Î Do not open or remove the packaging
until immediately before lifting to install
the regulator into the pipeline.
Î Leave the regulator in its transport con-
tainer or on the pallet to transport it on
site.
Î Do not remove the protective caps from
the inlet and outlet until immediately
before installing the regulator into the
pipeline. They prevent foreign particles
from entering the regulator.
Î Dispose and recycle the packaging in
accordance with the local regulations.