Test running

1. PRECAUTIONS IN TEST RUNNING
• The initial power supply must provide at least 90% of the rated voltage. Otherwise, the air conditioner
should not be operated.
CAUTION
• To cancel the test run, press any button.
CHECK THE FOLLOWING ITEMS WHEN INSTALLATION IS COMPLETE
• After completing work, be sure to measure and record trial run properties, and store measured data, etc.
• Measuring items are room temperature, outside temperature, suction temperature, blow out temperature,
wind velocity, wind volume, voltage, current, presence of abnormal vibration and noise, operating pressure,
piping temperature, compressive pressure.
• As to the structure and appearance, check following items.
□Is the circulation of air adequate?
□Is the draining smooth?
□Is the heat insulation complete
(refrigerant and drain piping)?
□Is there any leakage of refrigerant?
2. Connection of power supply
1. Connect the power supply cord to the independent power supply.
• Circuit breaker is required.
2. Operate the unit for fifteen minutes or more.
3. Evaluation of the performance
1. Measure the temperature of the intake and discharge air.
2. Ensure the difference between the intake temperature and the
discharge one is more than 8°C (Cooling) or reversely (Heating).
CAUTION: After the confirmation of the above conditions, prepare the wiring as follows:
1) Never fail to have an individual power specialized for the air conditioner. As for the method
of wiring, be guided by the circuit diagram pasted on the inside of control box cover.
2) Provide a circuit breaker switch between power source and the unit.
3) The screw which fasten the wiring in the casing of electrical fittings are liable to come
loose from vibrations to which the unit is subjected during the course of transportation.
Check them and make sure that they are all tightly fastened. (If they are loose, it could
give rise to burn-out of the wires.)
4) Specification of power source
5) Confirm that electrical capacity is sufficient.
6) Be sure that the starting voltage is maintained at more than 90 percent of the rated
voltage marked on the name plate.
7) Confirm that the cable thickness is as specified in the power sources specification.
(Particularly note the relation between cable length and thickness.)
8) Never fail to equip a leakage breaker where it is wet or moist.
9) The following troubles would be caused by voltage drop-down.
• Vibration of a magnetic switch, damage on the contact point there of, fuse breaking,
disturbance to the normal function of a overload protection device.
• Proper starting power is not given to the compressor.
HAND OVER
:
Teach the customer the operation and maintenance procedures, using the
operation manual (air filter cleaning, temperature control, etc.).
□Is the remote controller switch operated?
□Is there any faulty wiring?
□Are not terminal screws loosened?
M4......118N . cm{12kgf . cm}
M6......245N . cm{25kgf . cm}
Test running
M5......196N . cm{20kgf . cm}
M8......588N . cm{60kgf . cm}
Thermometer
Installation Manual 15