2.2 Mechanical installation
The MBP supports two installation modes: Tower installation and rack installation. The MBP
should be located at the top (rack installation), or to the left (tower installation) of the power
module for cable connection access. (as shown below)
Rack installation
Allow for 500mm front and rear clearance from the module for ventilation
Do not carry the front/rear panel of the module during installing.
2.2.1 Rack mount
The Installation steps are the same as that of the UPS Power module. The MBP is suitable for
installation in a 19-inch standard rack cabinet. It is recommended that the depth of the cabinet
be no less than 800mm.
Install the optional rail kit. This rail kit is '2U & with M5 sized screw holes, the depth of
1.
the rail kit is: 415-763mm.
13
Tower installation