Installing stays (anti-vibration measure)
Install stays from the top of the hull unit to the ship's hull. The stays should be angle iron with
a size of 75 x 75 x 9 mm or more and at least two pieces should be used; one each to ship's bow
and stern directions. Install if possible, two more stays in ship's transverse direction.
Do not install the stays as shown below. Vibration-resistance effect is reduced since vibration is
applied to the stays as rotation force. Install them horizontally.
Figure 3-8 Wrong installation of stay
Fastening receiver unit to hull unit
Fasten the receiver unit to the left side of the hull unit as shown at right.
A transducer cable protection cover has been fitted where the receiver unit is to be fastened to
the hull unit. Remove it when mounting the receiver unit.