Kohler PowerWAVE 6000 User Manual page 27

60-120 kva s3
Table of Contents

Advertisement

this is the case, you should pre-install the power and control cables to ensure that they are fully accessible once the UPS
is fixed in its final position.
Where the UPS cabinet is installed adjacent to the CBAT 150T battery cabinet a rear clearance of 505 mm (D) is applied
to align the front of the cabinets.
Side clearance (E),(F)
The CBAT 150T battery cabinet and UPS cabinet do not require any side clearance, so they can be installed immediately
adjacent to each other or partition/wall (E). However, it is necessary to open the cabinet door to 115º to fully access some
internal components, so, if the cabinet is installed adjacent to a partition or wall that extends beyond the front edge of the
cabinet a right side clearance of 100 mm (F) should be provided to allow the door to open fully.
Note: If it is not possible to apply the additional right-side clearance the doors have been designed to be easily removable
to aid internal access when needed.
Battery installation
Although a CBAT 150T battery cabinet is shown in Figure 3.1, the design of the battery installation is bespoke to the
individual site. However, we recommend that where possible the battery is contained in a purpose-designed cabinet
installed immediately adjacent to the UPS cabinet. It can be positioned on either side of the UPS cabinet but ideally it
should be installed to the left of the UPS to minimise the length of the interconnecting DC cables.
Key Point: Although the CBAT 150T cabinet does not require any side or rear clearance for ventilation
purposes, this may differ with other battery cabinet designs.
If the battery is to be mounted in an external battery rack rather than in a battery cabinet, we recommend that the battery
installation is as close as possible to the UPS cabinets to minimise the length of the DC cable runs. The battery cables
must be sized to compensate for the DC voltage drop between the battery installation and UPS.
Contact Kohler Uninterruptible Power Ltd for installation advice and support if necessary.
TS_610_01 PowerWAVE 6000 S3 (60-120kVA) User Manual 21/10/19
3: Installation Planning
19