To Perform A Test Run - Daikin Sky Air Advance Series Installation Manual

Hide thumbs Also See for Sky Air Advance Series:
Table of Contents

Advertisement

In case a wireless user interface is used: The indoor unit
decoration panel with infrared receiver is installed.
The outdoor unit is properly mounted.
The following field wiring has been carried out according
to this document and the applicable legislation:
▪ Between the local supply panel and the outdoor unit
▪ Between the outdoor unit and the indoor unit (master)
▪ Between the indoor units
There are NO missing phases or reversed phases.
The system is properly earthed and the earth terminals
are tightened.
The fuses or locally installed protection devices are
installed according to this document, and have NOT been
bypassed.
The power supply voltage matches the voltage on the
identification label of the unit.
There are NO loose connections or damaged electrical
components in the switch box.
The insulation resistance of the compressor is OK.
There are NO damaged components or squeezed
pipes on the inside of the indoor and outdoor units.
There are NO refrigerant leaks.
The correct pipe size is installed and the pipes are
properly insulated.
The stop valves (gas and liquid) on the outdoor unit are
fully open.
5.2

To perform a test run

This task is only applicable when using the BRC1E52 or BRC1E53
user interface. When using any other user interface, see the
installation manual or service manual of the user interface.
NOTICE
Do not interrupt the test run.
INFORMATION
Backlight. To perform an ON/OFF action on the user
interface, the backlight does not need to be lit. For any
other action, it needs to be lit first. The backlight is lit for
±30 seconds when you press a button.
1 Perform introductory steps.
#
1
Open the liquid stop valve and gas stop valve by
removing the cap and turning counterclockwise with a
hex wrench until it stops.
2
Close the service cover to prevent electric shocks.
3
Turn ON power for at least 6 hours before starting
operation to protect the compressor.
4
On the user interface, set the unit to cooling operation
mode.
2 Start the test run
#
Action
1
Go to the home menu.
RZA200+250D7Y1B
Sky Air Advance-series
4P573384-1 – 2019.04
Action
Result
Cool
Set to
28
°C
#
Action
2
Press at least 4 seconds.
3
Select Test Operation.
4
Press.
5
Press within 10 seconds.
3 Check operation for 3 minutes.
4 Check operation of the airflow direction (only applicable for
indoor units with swing flaps).
#
Action
1
Press.
2
Select Position 0.
3
Change the position.
4
Press.
5 Stop the test run.
#
Action
1
Press at least 4 seconds.
2
Select Test Operation.
3
Press.
5 Commissioning
Result
The Service Settings menu
is displayed.
Service Settings
1/3
Test Operation
Maintenance Contact
Field Settings
Demand
Min Setpoints Differential
Group Address
Return
Setting
Test Operation is
displayed on the home
menu.
Cool
Test Operation
Return
Setting
Test run starts.
Result
Air Volume/direction
Air Volume
Direction
Low
Position 0
Return
Return
Setting
Setting
Air Volume/direction
Air Volume
Direction
Low
Position 0
Return
Return
Setting
Setting
If the airflow flap of the
indoor unit moves,
operation is OK.
If not, operation is not OK.
The home menu is
displayed.
Result
The Service Settings menu
is displayed.
Service Settings
1/3
Test Operation
Maintenance Contact
Field Settings
Demand
Min Setpoints Differential
Group Address
Return
Setting
The unit returns to normal
operation, and the home
menu is displayed.
Installation manual
15