The burner should be controlled via a sequence programmer,
approved according the local standards. For connections, please
refer to the related wiring diagrams.
Warning:
Wiring to the burner must be in accordance with
current wiring standards. It is vital that the live
and neutral wires are connected correctly as
reversal could present a hazard. Also the earth
bonding must be checked to ensure a good con-
nection. (Wiring diagrams are provided with this
Guide)
GAS PIPEWORK MUST NOT BE USED FOR
EARTHING PURPOSES.
If burner control signals are supplied via a flame
safeguard control panel provided by others,
Eclipse Combustion can not accept any respon-
sibility for incorrect interfacing.
To verify the system was properly installed, perform the
following checks:
1. Be sure there are no leaks in the gas lines.
2. Be sure all wiring is properly connected.
3. Be sure all interlocks are working properly.
4. Be sure correct air and gas pressures are available.
5. At systems with high negative or positive process pressures,
take care that pressure switches and pressure regulators
(purge air) are cross connected to the process pressure.