Installation and operating instructions for:
R382, DN 15 - 50 reduced bore; R384, DN 15 - 50 reduced bore;
R392, DN 8 - 40 full bore; R394, DN 8 - 40 full bore
SAFETY PRECAUTIONS
Whenever a valve is being installed or removed
from the pipeline, ensure the line is not
pressurized and any hazardous medium is
drained away. Slowly cycle the valve several times
to relieve the cavity area and leave in the open
position.
Check that the seat and body pressure ratings
are suitable for the service prior to installation.
These ratings must not be exceeded.
STORAGE INSTRUCTIONS
The valves ball, seats and end connections
should be adequately protected against
damage.
The protective end covers should not be
removed until ready for installation.
GENERAL
All valves are bi-directional, controlling flow
in either direction. They can be installed in any
position, horizontally or vertically.
Thread tape or sealant is recommended to
ensure effective sealing. Check that the tape/
sealant is suitable for the service.
Emerson.com/FinalControl
MAINTENANCE
The only routine maintenance required is
periodical checks and adjustment to the
stem assembly. Adjustment to the gland
nut is recommended after the first 5000 and
10000 cycles; and every 10000 cycles thereafter
to compensate for the bedding of thrust and
gland seal and ensure leak free operation.
When tightening the gland nut, do not exceed
recommended torques, see table overleaf. After
reaching recommended gland nut torque, back
off to nearest flat on nut. Bend the lock washer
over the nut in this position.
When fitting actuators to valves, refer
to mounting instructions supplied with
mounting kit.
INSTALLATION
Prior to leaving the factory each valve is
pressure tested, and to prevent damage to the
ball surface and seats protective covers will
have been fitted. Leave these in place until
such time as the valve is ready for installation.
On removal make sure the valve is in the open
position and free of foreign matter.
© 2017 Emerson. All Rights Reserved.
When installing valve, follow relevant standards
and statutory regulations.
Examples:
Local gas fitting regulations, municipal building
codes or electrical wiring regulations.
a) Screwed valves: valves should not be
dismantled prior to fitting, and installed as
a unit following standard piping practice
(eg. using thread tape or pipe sealant).
When screwing the valve to the pipe
DO NOT OVERTIGHTEN.
b) Weld valves: follow instructions for weld
valves (see overleaf).
PIPE COMPATIBILITY
Emerson ball valves are suitable for installation
into most piping systems. The standard end
connections are:
• BSPT
• NPT
• Socket weld pipe Sch. 40
• Socket weld O/D tube Sch. 10
• Butt weld pipe Sch. 40
Other end connections are available upon
request.
VCIOM-02975-EN 18/02

Advertisement

loading

Summary of Contents for Emerson KTM RICHARDS FIGURE R384

  • Page 1 When screwing the valve to the pipe DO NOT OVERTIGHTEN. b) Weld valves: follow instructions for weld valves (see overleaf). PIPE COMPATIBILITY Emerson ball valves are suitable for installation into most piping systems. The standard end connections are: • BSPT SAFETY PRECAUTIONS MAINTENANCE •...
  • Page 2 Responsibility for proper selection, use, and maintenance of any product remains solely with the purchaser and end user. KTM is a mark owned by one of the companies in the Emerson Automation Solutions business unit of Emerson Electric Co. Emerson Automation Solutions, Emerson and the Emerson logo are trademarks and service marks of Emerson Electric Co.

This manual is also suitable for:

Ktm richards figure r392Ktm richards figure r394