Recommended procedure - Part II: Software
Table 8-2

Recommended commissioning procedure - Part II: Software

Tasks
Switch on the PG
and start SIMATIC
Manager
Download the
configuration and the
program to the CPU
Testing the I/Os
Commission
PROFIBUS-DP or other
networks
Connect the outputs
Danger
Proceed step-by-step. Do not go to the next step unless you have verified the
previous one without error/error message.
Reaction to errors
React to errors as follows:
• Check the system with the help of the Checklist in the chapter below.
• Check the LED displays on all modules. Notes on their significance is found in
the chapters describing the respective modules.
• If required, remove specific modules to trace the error.
Important notes are also found ...
in Chapter Testing Functions, diagnostics and fault elimination
S7-300 Programmable Controller Hardware and Installation
A5E00105492-01
Remarks
-
Helpful functions are here:
Monitoring and controlling of variables
Testing with program status
Force
Controlling outputs in Stop mode (PA
isolation)
Tip: If you connect switches to the inputs, you
can include the signal lines in your test.
-
Commissioning the outputs successively.
Commissioning
Information is found in
...
in the STEP 7
Programming Manual
in the STEP 7
Programming Manual
in Chapter Testing
Functions, Diagnostics
and Fault Elimination
in Chapter Commissioning
PROFIBUS-DP
-
8-3

Advertisement

Table of Contents
loading

Table of Contents