2. MECHANICAL PARTS REPLACEMENT PROCEDURE
2-1. Cleaning Roller Unit
(Removal)
1. Remove the Mechanism Unit.
2. Unscrew the 2 screws (A) and (B), then remove the Cleaning Roller Unit.
(Installation)
1. Hook the portion (B) of Cleaning Roller Unit to portion (A) of Mechanism Chassis and install the Cleaning Roller
Unit. Then be careful the Release Arm does not run onto the part at end of sub chassis (C) as shown in figure
B.
NOTE: Supply the voltage to loading motor and the Cleaning Roller Unit is installed in the mechanical position as
shown in figure (B) to simple installation (No problem it installation in loading complete position).
2. Tighten the Screw (A) and (B) as shown in figure A. When tighten the screw (B), flexible cable also tighten up
together as shown in figure A.
(Confirmation of Operation)
1. To confirm that the Cleaning Roller operates normally on the Mechanism Unit, supply the voltage to loading
motor and confirm that the Cleaning Roller touches the Cylinder in loading operation.
UNLOADING.............A: +4.5V B: GND
LOADING ..................A: GND
SCREW (B)
(C)
(A)
(A)
(B)
B: +4.5V
Cleaning Roller Unit
Figure A
Figure B
Figure C
MECH-12
SCREW (A)
Release Arm
(B)