Siemens Simatic PCS 7 Commissioning Manual page 32

Process control system foundation fieldbus
Hide thumbs Also See for Simatic PCS 7:
Table of Contents

Advertisement

Engineering
4.2 Configuring
6. Repeat steps 4 and 5 for other interconnections.
7. When you have created all interconnections, click "Save".
Download
The schedule for the FOUNDATION Fieldbus is calculated automatically during the download
to the FF devices.
Additional information
● Online help for SIMATIC PDM
32
The interconnections will be saved in the project.
Commissioning Manual, 03/2013, A5E03880935-02
FOUNDATION Fieldbus