Section 2 - Rigging And Lifting; Form 1 Total Weight; Form 1 Shipment; Unit Rigging - York YMC2 Installation And Assembly Manual

Centrifugal liquid chillers with optiview control center
Hide thumbs Also See for YMC2:
Table of Contents

Advertisement

FORM 160.84-N1
ISSUE DATE: 11/22/2016
Improper use of rigging equipment can
result in serious injury. Do not operate
without proper training and authorization.
It is the responsibility of the installer to
have a qualified and certified crane opera-
tor and rigger for lifting components and
relocating to the new site.
To perform a safe and effective rigging practice the
installer is responsible for inspection and operation
of the lifting equipment, special site considerations,
proper rigging and lifting practices, and any safety
considerations.
Particular items the installer must be aware of are:
• Rope with no visible wear, twisted, kinked, or
damaged chains.
• Deformed, cracked, or stretched hooks or safety
latch on the hook is not damaged.
• Correct drum spooling as the hook is raised.
• Do not operate a damaged or malfunctioning
hoist.
• Do not wrap the hoisting rope or chain around the
load.
• Do not lift loads over people.

FORM 1 TOTAL WEIGHT

The heaviest possible YMC² combination of total
weight for Form 1 shipment is 33,863 lbs (15,360 kg)
or 17 ton. See Weights on page 73 for YMC² weight
breakdown.
The actual unit total shipping and operat-
ing weight is on the submittal drawings.
JOHNSON CONTROLS

SECTION 2 - RIGGING AND LIFTING

FORM 1 SHIPMENT

The chiller is shipped complete with miscellaneous
items shipped together with refrigerant charges are in-
cluded.
• The unit is completely assembled at the factory.
• The driveline (compressor/motor assembly) is
mounted and all the necessary interconnecting
piping is assembled.
• The complete unit is factory leak-tested, evacu-
ated and shipped charged with refrigerant.
• The OptiView™ Control Center is mounted on
the unit.
• The Power Panel is mounted on the unit.
• The Variable Speed Drive (VSD) is mounted,
wired, and ship with glycol.

Unit Rigging

One lifting chain is required for each lift-
ing point and each chain having a work-
ing load limit 30% of unit total weight.
The lifting chains traversing the evapora-
tor/condenser shells should remain 90°
+/- 10° from horizontal. A spreader bar
may be required to achieve the +/- 10°.
1. Attach rigging chains to an adequate lifting device.
2. Attach chains to the lifting holes at the corner of
each end sheet as shown on Figure 2 on page 16.
3. If necessary to avoid contact with chiller compo-
nents install side spreader bars between the Evap-
orator and Condenser end sheet lifting chains.
4. The angle of the lifting chains traversing the en
sheet should not be less than 65° as shown on Fig-
ure 2 on page 16.
5. With an adequate lifting device lift the unit slight-
ly off the ground to determine adjustments neces-
sary to keep the unit level. Make adjustments as
necessary to level the unit.
2