Requirement
All valves are closed.
Procedure
To commission the transmitter for steam or liquid, proceed as follows:
1. Open the shut-off valve for the test connection
2. Via the test connection of the shut-off module
pressure transmitter
3. Check the start of scale value.
4. If the start of scale value differs from the value desired, correct it.
5. Close the shut-off valve for the test connection
6. Open the shut-off valve
7. Open the shut-off valve for the process

Commissioning for gases

Usual arrangement
Measuring gases above the pressure tapping point
20
.
at the pressure tapping point.
.
.
, apply the pressure corresponding to the start of scale value to the
.
Special arrangement
Measuring gases below the pressure tapping point
SITRANS P300 (7MF8.23.. 7MF8.24.. 7MF8.25..)