Block to be
Re-Loaded
Series A
IOMs
Series C
IOMs
CM
IOLINK
R301.1
11/06
Conditions or Restrictions
•
The IOM block loads the IOM's parameters to the IOLINK followed
by all the previously loaded channels.
•
The IO Channel blocks assigned to CMs that have not been
previously loaded, will not be loaded.
•
The C300 FTEB I/O Manager retains IOM configuration so it can
restore configuration if the IOM(s) are not available at load time.
•
Channel blocks that are assigned and have not been previously
loaded, will not be loaded.
•
The C300/CEE, IOLINK and IOMs whose channels are assigned to
the CM must be previously loaded.
The CM reload operation loads the CM block and any assigned IO
•
Channel blocks to the associated CEE and also loads the contained
PMIO Channel block parameters to the IOLINK block and its
associated IOM.
•
CM reload fails if any of the following errors are encountered:
−
The I/O Channel's associated IOM block has not been
previously loaded.
−
The CEE block is not present and loaded.
−
The IOLINK block (if PMIO Channels are assigned to the CM)
is not present and loaded.
−
The C300 block is not present and loaded.
The CM is ACTIVE
−
Contained PMIO Channels are ACTIVE
−
The state of any PMIO IOM whose assigned channels are
−
contained in the CM is RUN.
•
The C300 Block must be present and previously loaded.
•
The state of previously loaded IOMs must be IDLE.
•
IOLINK block configuration parameters are re-loaded along with
configuration data for previously loaded IOM Blocks.
•
Re-load fails and is cancelled if the C300 is not loaded, or the state
of at least one previously loaded IOM is in RUN.
Experion C300 Controller User's Guide
Honeywell
Reloading components from project
Loading IOMs and CMs
155