Removal And Reinstallation Of The Control Circuit Terminal Block - Mitsubishi Electric FR-CC2-H355K Instruction Manual

F800 series, fr-f802 separated converter type
Hide thumbs Also See for FR-CC2-H355K:
Table of Contents

Advertisement

Smoothing capacitors
A large-capacity aluminum electrolytic capacitor is used for smoothing in the main circuit DC section, and an aluminum
electrolytic capacitor is used for stabilizing the control power in the control circuit. Their characteristics are deteriorated by the
adverse effects of ripple currents, etc. The replacement intervals greatly vary with the surrounding air temperature and
operating conditions. When the inverter is operated in air-conditioned, normal environment conditions, replace the capacitors
about every 10 years.
The appearance criteria for inspection are as follows:
• Case: Check the side and bottom faces for expansion.
• Sealing plate: Check for remarkable warp and extreme crack.
• heck for external crack, discoloration, liquid leakage, etc. Judge that the capacitor has reached its life when the measured
capacitance of the capacitor reduced below 80% of the rating.
NOTE
• The inverter diagnoses the control circuit capacitor by itself and can judge its life. (Refer to the Instruction Manual (Detailed)
of the FR-F800)
Relay output terminals
• To prevent a contact fault, etc., relays must be replaced according to the cumulative number of switching times (switching life).
• The control terminal block must be replaced in case of failure of either relay connected to the relay output terminals A1, B1,
and C1, or A2, B2, and C2.
Main circuit fuse
A fuse is used inside the inverter. The replacement intervals vary with the surrounding air temperature and operating
conditions. When the converter unit is operated in air-conditioned, normal environment conditions, replace the capacitors
about every 10 years.
5.1.7
Removal and reinstallation of the control circuit
terminal block
The FR-F800 series inverter has a removable control circuit terminal block, which can be replaced with a new one or a control
terminal option.
Removal and reinstallation
1) Loosen the two mounting screws at the both side of the control circuit terminal block. (These screws cannot be removed.)
Slide down the control circuit terminal block to remove it.
Loosen the screws
2) Be careful not to bend the pins of the inverter's control circuit connector, reinstall the control circuit terminal block and fix it
with the mounting screws.
NOTE
• Before starting inverter replacement, switch power OFF, wait for at least 10 minutes, and then check the voltage with a tester
and such to ensure safety.
PRECAUTIONS FOR MAINTENANCE AND INSPECTION